Ontario Superior Court orders Burlington Airpark Inc. to pay city $118,000

City of Burlington Press Release – Nov. 8, 2016

The Ontario Superior Court of Justice has ordered Burlington Airpark Inc. to pay City of Burlington court costs in the amount of $118,327.53.

The cost award is related to the June 30, 2016 decision of the Ontario Superior Court of Justice in favour of the City of Burlington’s application to compel Burlington Airpark Inc. to submit an application for a site alteration permit to comply with the city’s bylaw. With the court ruling, the Airpark was required to file an application for a site alteration permit for the fill deposited between 2008 and 2013 before Aug. 31, 2016 and has now been ordered to pay the city’s court costs on a substantial indemnity basis.

An appeal by Burlington Airpark Inc. to the June 30, 2016 judgement in favour of the City of Burlington is scheduled to be heard by the Ontario Court of Appeal on March 28, 2017 at Osgoode Hall, 130 Queen St. West in Toronto.

The City of Burlington site alteration bylaw 64-2014 regulates the placing, dumping, cutting and removal of fill or the alteration of grades or drainage on a piece of land. Individuals doing this type of work must first submit an application to the city for a site alteration permit.

For more information, visit www.burlington.ca/airpark

-30-

Communications contact:

Donna Kell
Manager of Communications
Office: 905-335-7600, ext. 7841
Cell: 905-630-6263
email: donna.kell @burlington.ca

 

I was inspired to seek public office because I believe, like so many of you, “I can do something about that” on the issues we face. As councilor, my role is to take a stand on what’s best for residents and go to bat for it. Pushback is inevitable from those who don’t have the community’s interests at heart. I will stand with you and for you, to achieve the best interests of our city, without caving to unacceptable compromise in the name of consensus.

What's your take?